The Executive Engineer, Irrigation Project, Strengthening Division, Tuljapur v. Balu Eknath Kokate Died His Legal Heirs Surekha And ORS
2025:BHC-AUG:22321 1 986 ca 7534.25
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 7534 OF 2025 IN CIVIL APPLICATION NO. 10795 OF 2024 IN FIRST APPEAL NO. 1939 OF 2025 The Executive Engineer Irrigation Project Strengthening Division Tuljapur .. Applicant
Versus
Balu Eknath Kokate Since deceased through L.Rs.
Surekha and others .. Respondents Shri Uday S. Malte, Advocate for the Applicant through V.C. Shri B. A. Shinde, A.G.P. for the Respondent/State. CORAM : SHAILESH P. BRAHME, J.
DATE : 14TH AUGUST, 2025.
FINAL ORDER :
.
Present appeal is similarly circumstanced with First Appeal No. 1938 of 2025. In that appeal by my order dated 05.08.2025 cost imposed came to be waived. On the ground of parity, I propose to follow same course. The cost imposed by earlier order dated 24.06.2025 in Civil Application No. 10795 of 2024 shall stand waived. The civil application is allowed in terms of prayer clause 'B'. The civil application is disposed of. [ SHAILESH P. BRAHME J. ] bsb/Aug. 25