Godhavari Maratwadha Irrigation Dev.Co. Aurangabad Thr Its Ex.Engineer, Osmanabad Minor Irrgation v. Anil Dattatrya Suryawanshi And Others
(1) 918-ca-3508-2023
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.3508 OF 2023 IN FAST/21467/2020 GODHAVARI MARATWADHA IRRIGATION DEV.CO.
AURANGABAD THR ITS EX.ENGINEER, OSMANABAD MINOR IRRGATION
VERSUS
ANIL DATTATRYA SURYAWANSHI AND OTHERS ...
Mr. Madhav P. Gude, Advocate for the Applicant. Mr. A. B. Chate, AGP for Respondents-State.
...
CORAM : S. G. CHAPALGAONKAR, J.
DATE : 20th JULY, 2023.
PER COURT:- 1.
By this application, the applicant/acquiring body seeks to condone the delay of 1720 days caused in filing the appeal against the judgment and order passed by the Reference Court, Osmanabad in LAR No.700/2013.
2.
The learned Advocate appearing for the applicant submits that the delay is caused on account of administrative and procedural compliance. The applicant has not derived any disadvantage out of such delay. He invites attention of this Court to the reasons given in paragraph nos.2 and 3 of the application to contend that the necessary steps were taken by the acquiring body without wasting much time.
3.
Notice of this application is served upon the respondents. However, none appears for the respondents.
(2) 918-ca-3508-2023 4.
The contents of the paragraph nos.2 and 3 of the application are uncontroverted, which makes out sufficient cause to condone the delay. Hence, the following order:-
ORDER
a.
The Civil Application is allowed.
b.
Delay of 1720 days caused in filing the appeal is condoned. c.
Appeal be registered.
5.
Civil Application is disposed of.
(S. G. CHAPALGAONKAR) JUDGE Devendra/July-2023