← Library
Bombay High CourtCP/575/2022disposed off

Pundlik Tukaram Mote v. The State Of Maharashtra Through Secretary And Others

2022-09-23Hon'Ble Shri Justice Ravindra V. Ghuge,Hon'Ble Shri Justice Arun R. Pedneker3 pages

(1)

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 907 CONTEMPT PETITION NO.133 OF 2021 IN WP/10558/2019 SHIVAJI GOVINDRAO YERANDE AND OTHERS

VERSUS

THE STATE OF MAHARASHTRA AND OTHERS AND 908 CONTEMPT PETITION NO.134 OF 2021 IN WP/14592/2019 RAMESH BAPURAO MULE AND OTHERS

VERSUS

THE STATE OF MAHARASHTA AND OTHERS ....

Mr S. G. Rudrawar, Advocate for petitioners;

Mr S. G. Karlekar, A.G.P. for respondents/State AND 910 CONTEMPT PETITION NO.575 OF 2022 IN WP/354/2021 PUNDLIK TUKARAM MOTE

VERSUS

THE STATE OF MAHARASHTRA THROUGH SECRETARY AND OTHERS ....

Mr D. R. Irale Patil, Advocate for petitioner; Mr P. S. Patil, A.G.P. for respondents/State Mr U. B. Bondar, Advocate for respondent/Z.P. Aurangabad CORAM : RAVINDRA V. GHUGE AND ARUN R. PEDNEKER, JJ.

DATE : 23rd September, 2022

(2) PER COURT:

1.

The learned A.G.P. submits that, he has forwarded a communication dated 08/09/2022 to the five different Departments with reference to the pending contempt petitions, involving either of these Departments. It has been conveyed to these Departments in the light of the discussion during the course of the hearing of the contempt petitions earlier, that, the Departments should either acquire the orders, which would restrain the petitioners from seeking payment of dues or make an arrangement for obeying the directions of this Court, till 31/12/2022.

2.

The learned A.G.P. has also conveyed to the Departments that, a group of review applications, filed by the Departments, were dismissed by a common Judgment and order dated 30/08/2020.

3.

By a communication dated 15/09/2022, the Deputy Secretary Smt. Leena Sankhe, has informed the learned A.G.P. that, the Government will take appropriate steps with regard to the orders passed by this Court, for obtaining stay orders, lest, by

(3) 31/12/2022, necessary corrective steps will be taken, if no stay is obtained.

4.

These two communications (3 pages) are taken on record and marked 'X-1' collectively for identification. 5.

The learned Advocates for the petitioners are satisfied that, if the Departments are unable to obtain orders from the Hon'ble Supreme Court, they would make the payments of the petitioners, on or before 31/12/2022. They, therefore, submit that, these petitions can be disposed off.

6.

In view of the above, these petitions stand disposed off. (ARUN R. PEDNEKER, J.) (RAVINDRA V. GHUGE, J.) sjk