IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 924 CIVIL APPLICATION NO.11792 OF 2022 IN FAST/21506/2022 THE EXECUTIVE ENGINEER HATNUR PROJECT CHOPDA

VERSUS

THE STATE OF MAHARASHTRA & OTHERS ...

Advocate for Applicant : Mr.S.V.Mundhe AGP for Respondent-State : Mr.A.B.Chate Advocate for Respondent nos.3 to 13 : Mr.Vijay B.Patil ...

CORAM : S.G.DIGE, J.

DATE : 18.08.2022 P.C. :

1] Heard the learned counsel for the applicant.

2] Issue notice to the respondents. Mr. Vijay B. Patil, learned counsel waives notice for respondent nos.3 to

13. The learned AGP waives notice for respondent nos.1 and 2.

3] The learned counsel for respondent nos.3 to 13 has no objection to condone the delay.

4] Considering the submissions of all learned counsel and the reasons mentioned in the application, delay

11792.22CA of 101 days for filing First Appeal is condoned. Appeal be registered subject to removal of office objections, if any. 5] Civil Application is disposed of accordingly. [S.G.DIGE] JUDGE DDC