Bombay High CourtCA/10589/2019delay condonatedrejected

The G.M.I.D.C., Thr The Ex. Engineer, Minor Irrigation Division, Latur And ORS v. Babu Honaji Rathod

2020-11-02Hon'Ble Shri Justice V.K. Jadhav3 pages

{1}

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.10593 OF 2019 IN FIRST APPEAL ST.NO.22992 OF 2018 Godavari Marathwada Irrigation Development Corporation, Latur & others Applicants

Versus

Ramesh Rupchand Rathod Respondent Mr.A.M.Gaikwad, advocate for the applicants. Mr.Gopal D. Kale, advocate for the Respondent. WITH CIVIL APPLICATION NO.10583 OF 2019 IN FIRST APPEAL ST.NO.22680 OF 2018 WITH CIVIL APPLICATION NO.10591 OF 2019 IN FIRST APPEAL ST.NO.22970 OF 2018 WITH CIVIL APPLICATION NO.10599 OF 2019 IN FIRST APPEAL ST.NO.22973 OF 2018 WITH CIVIL APPLICATION NO.10581 OF 2019 IN FIRST APPEAL ST.NO.22976 OF 2018 WITH CIVIL APPLICATION NO.10589 OF 2019 IN FIRST APPEAL ST.NO.22980 OF 2018 WITH CIVIL APPLICATION NO.10585 OF 2019 IN FIRST APPEAL ST.NO.22983 OF 2018 WITH CIVIL APPLICATION NO.10595 OF 2019 IN FIRST APPEAL ST.NO.22989 OF 2018 WITH CIVIL APPLICATION NO.10601 OF 2019 IN FIRST APPEAL ST.NO.22995 OF 2018 WITH CIVIL APPLICATION NO.10597 OF 2019 IN FIRST APPEAL ST.NO.23083 OF 2018 WITH

{2} CIVIL APPLICATION NO.10587 OF 2019 IN FIRST APPEAL ST.NO.22986 OF 2018 CORAM : V.K.JADHAV, J.

DATE : 02nd November, 2020.

PC :

Learned Counsel for the Respondent-original claimant/s appears and waives notice.

Heard both the sides.

There is delay of 553 days caused in fling the respective appeals against the judgment and award passed by the Reference Court. The delay has occurred due to completion of administrative formalities, such as approval, etc. Learned Counsel for the Respondent-claimants, though resisted the applications, however, it appears that the applications, seeking condonation of delay, are not resisted by fling any reply.

Thus, considering entire aspects of the case and since the original claimants have been permitted to withdraw the amount of compensation, deposited in this Court by the

{3} acquiring body, delay of 553 days caused in preferring the respective appeals is hereby condoned.

Civil Applications are allowed in terms of prayer clause "A" and are accordingly disposed of.

(V.K.JADHAV) JUDGE adb