Executive Engineer Medium Project K.K.V.M. Division Osmanabad v. Shrikant Sugriv Bhore And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD (1) CA NO.10407/2014gr 925 CIVIL APPLICATION NO. 10407 OF 2014 IN FAST/22611/2014 WITH CA/10409/2014 IN FAST/22656/2014 WITH CA/10411/2014 IN FAST/22667/2014 WITH CA/10414/2014 IN FAST/22664/2014 WITH CA/10416/2014 IN FAST/22670/2014 WITH CA/10418/2014 IN FAST/22674/2014 EXECUTIVE ENGINEER MEDIUM PROJECT K.K.V.M. DIVISION OSMANABAD
VERSUS
JOTIRAM TULSIRAM MANE AND OTHERS ...
Advocate for Applicant :Mr. Sangle Shirish G. AGP for Respondent State: Mr. S.P.Sonpawale Advocate for respondent no.1.: Mr. S.G.Kawade ...
CORAM : P.R. BORA, J.
Dated: June 09, 2017 ...
PER COURT :- 1.
Learned Counsel Shri Kawade appears for respondent no.1 in C.A.No.10414/2014. Service complete. 2.
Delay of 182 days has been caused in filing these appeals by the acquiring body. For the reasons stated in the applications which, according to me, are just and sufficient, the delay of 182 days caused in filing the appeals is condoned. Civil Applications for condonation of delay stand disposed of. The agp/-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD (2) CA NO.10407/2014gr Appeals be registered in accordance with law. 3.
After registration of the appeals issue notice to the respondents in the appeals returnable on 19.6.2017. Shri Kawade, learned Counsel, waives service for respondents / original claimants in all the matters. Service complete. Call for R & P. Place the matters for admission on 19.6.2017. ( P.R. BORA, J. ) ...
agp/-