Bombay High CourtCA/7978/2024admittedallowedgrantedrule absolute

The Executive Engineer,Seena Kolegaon Project, Paranda, District Osmanabad v. Murlidhar Ramchandra Khaire And ORS

2025-03-13Hon'Ble Shri Justice S. G. Chapalgaonkar1 pages

{1} 77 sr.no..odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 7978 OF 2024 IN FAST/20933/2024 The Executive Engineer,seena Kolegaon Project, Paranda, District Osmanabad ....Applicant

VERSUS

Murlidhar Ramchandra Khaire And Ors .....Respondent .....

Advocate for Applicant : Mr. Kulkarni Mukul S. AGP for Respondents: Mr. D.B. Bhange.

CORAM : S.G. CHAPALGAONKAR, J.

DATE : 13TH MARCH, 2025.

P.C. :- 1.

Heard Mr. Kulkarni, learned advocate for applicant. Mr. Kulkarni undertakes to deposit deficit court fees within one week. 2.

Applicant seeks to condone delay of 241 days caused in fling the appeal.

3.

Perusal of reasons from para No. 3 shows that delay has been occasioned on account of administrative reasons. The applicant has not derived any advantage by making delay.

4.

Considering reasons as stated in the application, sufficient cause is made out to condone the delay. Delay of 241 days caused in filing appeal is condoned. Appeal be registered. [S.G. CHAPALGAONKAR, J] grt/-