← Library
Bombay High CourtCA/15594/2015admittedallowedgrantedrule absolute

Devidas Manku Bhil v. The Executive Engineer, Medium Project Division No.1, Dhule And Another

2016-01-15Hon'Ble Shri Justice T.V. Nalawade2 pages

CA 15594/15 in RC 550/15 in X-OBJ 3293/14 in FA 1697/10 - 1 -

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.15594/2015 IN REJECTED CASE NO.550/2015 IN CROSS OBJECTIONS NO.3293/2014 IN FIRST APPEAL NO.1697/2010 Devidas Manku Bhil.

...Applicant..

Versus

The Executive Engineer, Medium Project Division No.1, Dhule & another.

...Respondents...

.....

Shri S.V. Bhosle, Advocate h/f Shri R.C. Patil, Advocate for applicant.

Shri A.R. Borulkar, AGP for respondent no.2.

.....

CORAM: T.V. NALAWADE, J.

DATE: 15.01.2016 ORDER :

1] This application is filed for setting aside the order made by the learned Registrar (Judicial) by which registration of the cross-objections is refused. 2] Heard learned counsel appearing for the parties. 3] In view of the contents of the application and the

CA 15594/15 in RC 550/15 in X-OBJ 3293/14 in FA 1697/10 - 2 - submissions made, this Court holds that the application deserves to be allowed. There is delay of 204 days in filing the application. The delay is also condoned subject to condition that no interest will be payable in respect of this 204 days period if the cross-objections filed by the present applicant are allowed in future. The applicant undertakes to remove office objections prior to 29.1.2016 and pay the Court fees. If that is not done, it will be presumed that present application is rejected.

(T.V. NALAWADE, J.) ndk/c1511647.doc