← Library
Bombay High CourtCA/10941/2015admittedallowedgrantedrule absolute

The Executive Engineer, Lower Terna Project Canal, Division No.2, Latur And Others v. Satyabhamabai Madhav Yevate

2015-12-18Hon'Ble Shri Justice A.M. Badar1 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY,

AURANGABAD BENCH, AT AURANGABAD.

CIVIL APPLICATION NO. 10941 OF 2015 IN FAST/24523/2015 WITH CA/10943/2015 IN FAST/24572/2015 THE EXECUTIVE ENGINEER, LOWER TERNA PROJECT CANAL, DIVISION NO.2, LATUR AND OTHER

VERSUS

SATYABHAMABAI MADHAV YEVATE .........................

Mr. D.B. Pawar, Advocate, for applicants.

Non-applicant served (Absent).

..........................

CORAM : A.M. BADAR, J.

DATE : 18TH DECEMBER 2015 PER COURT :

1.

Heard Shri Pawar, the learned Counsel appearing for applicants / appellants. None appeared for non-applicants despite service. 2.

Perused applications. Delay of 707 / 708 days in lodging appeals under Section 54 of the Land Acquisition Act, 1894, is sufficiently explained. Applications are not objected to by non-applicants. 3.

Hence, for the stated reasons Applications are allowed in terms of prayer clause "B".

( A.M. BADAR ) JUDGE ................................

puranik / CA10941.15etc