The Executive Engineer Hatnoor Project Chopda v. Dinkar Gotu Patil
(1) 931 CA-15413.2022.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 931 CIVIL APPLICATION NO.15413 OF 2022 IN FAST/21971/2022 THE EXECUTIVE ENGINEER HATNOOR PROJECT CHOPDA
VERSUS
DINKAR GOTU PATIL ...
Mr. S.B. Kadu, Advocate for the applicant.
Mr. V.B. Patil, Advocate for the respondent.
...
CORAM :
SANDIPKUMAR C. MORE, J.
DATED :
16.11.2022.
ORDER:- 1.
Heard. Issue notice to respondent. Learned Counsel Mr. Patil waives notice for the respondent. 2.
Heard rival submissions. The delay appears to be only of 105 days and caused due to obtaining approvals at various stages. There is no strong objection from other side. As such, the delay of 105 days stands condoned. The appeal be placed for admission after removal of office objections, if any.
3.
The application is accordingly disposed of.
(SANDIPKUMAR C. MORE, J.) vd_dhirde