Raghunath Tulshiram Chavhan G.P.A. Holder Of Applicant No. 2 To 6 v. The Special Land Acquistion Officer Upper Tapi Project Hatnoor-2, Jalgaon And Another
-:(1):- 12215 FARAD CONTINUATION SHEET NO.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD.
Office Notes, Office Memoranda of Coram, appearance, Court's orders or directions and Registrar's orders.
Court's or Judge's orders.
CIVIL APPLICATION NO. 12215 OF 2015 IN FAST/24776/2015 RAGHUNATH TULSHIRAM CHAVHAN G.P.A. HOLDER OF APPLICANT NO. 2 TO 6
VERSUS
THE SPECIAL LAND ACQUISTION OFFICER UPPER TAPI PROJECT HATNOOR-2, JALGAON AND ANO ...
Advocate for Applicant :Mr. Kshirsagar Hemraj P. AGP for Respondent/ State: Mr. C. V. Dharurkar. *** CORAM: T. V. NALAWADE, J.
DATED:
12th JANUARY, 2016.
PER COURT:
1.
The application is filed for condonation of delay of 1947 days caused in filing appeal against judgment and Award of LAR No.917 of 2005. In view of the contents of the application and the submissions made, this Court holds that sufficient cause is shown. However, there will be question of making payment of interest for this period and so learned counsel for the Applicants makes a statement that the applicants, original claimant will not be claiming interest on the compensation amount, if granted in the
-:(2):- 12215 appeal.
2.
In view of this statement, the application is allowed. The delay of 1947 days is condoned subject to the condition that no interest will be payable for this period if the compensation is awarded.
[T. V. NALAWADE, J.] Dt.12/01/2016.
ans/12215