← Library
Bombay High CourtCA/9993/2024admittedallowedgrantedrule absolute

Vilash Balasaheb Bidwe v. The Executive Engineer Nimna Dudhna Project Shelu And ORS

2024-10-17Hon'Ble Shri Justice Kishore C. Sant2 pages

2024:BHC-AUG:26282 71 ca.9993.24.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY,

BENCH AT AURANGABAD.

71 CIVIL APPLICATION NO. 9993 OF 2024 IN FA/4629/2023 VILASH BALASAHEB BIDWE

VERSUS

THE EXECUTIVE ENGINEER NIMNA DUDHNA PROJECT SHELU AND ORS ...

Advocate for Applicant : Mr. Gaurav M. More Kumar. AGP for Respondent/State : Mr. K. S. Hoke Patil. Advocate for Respondent / Appellant : Mr. A. N. Gaddime. ...

CORAM :

KISHORE C. SANT, J.

DATE :

17th October, 2024.

P.C.:

.

Heard the learned counsel for the parties.

This application is for withdrawal of amount. The learned counsel for appellant opposes the application. However, looking to the fact that the judgment is delivered based on earlier judgments in land acquisition references arising out of same acquisition proceedings, the following order is passed:-

O R D E R

I.

The applicant is permitted to withdraw 50% of the amount alongwith accrued interest deposited in this Court on furnishing usual undertaking. Further 25% of the amount with accrued interest is allowed to be withdrawn on furnishing solvent surety/security to the satisfaction of the learned Registrar (Judicial) of this

71 ca.9993.24.odt Court. The remaining amount be kept in fixed deposit in any nationalized bank till disposal of the appeal. II.

With this, the civil application for withdrawal of amount stands disposed of.

[ KISHORE C. SANT, J. ] nga