The Executive Engineer, Lower Dudhana Project, Selu Thr Gmidc Aurangabad v. Vitthal Ramchandra Dongre And ORS
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 921 CIVIL APPLICATION NO. 12184 OF 2016 IN FAST/25880/2016 WITH CA/12186/2016 IN FAST/25526/2016 THE EXECUTIVE ENGINEER, LOWER DUDHANA PROJECT, SELU THR GMIDC AURANGABAD
VERSUS
VITTHAL RAMCHANDRA DONGRE AND ORS ...
AGP for Respondent State: Mr. A.M.Phule ...
CORAM : P.R. BORA, J.
Dated: October 27, 2016 ...
PER COURT :- 1.
Though respondent no.1 i.e. Original claimant is duly served, no one has entered appearance on his behalf. Delay of 459 and 437 days, respectively, has occurred in filing the present appeals.
2.
For the reasons stated in the applications which, according to me, are just and sufficient, the delay is condoned. Civil Applications for condonation of delay stand disposed of.
3.
The First Appeals be registered in accordance with law.
( P.R. BORA, J. ) AGP/-