The Executive Engineer Medium Project Osmanabad v. Maharudra Dharmraj Huke And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD.
8 CIVIL APPLICATION NO. 14547 OF 2015 IN FIRST APPEAL ST NO. 25295 OF 2014 The Executive Engineer, Medium Project .. Applicant
Versus
Maharudra Dharmraj Huke & Ors.
.. Respondents..
........
Mr R. C. Patil, Advocate for the applicant Mr S. A. Wakure, Advocate for respondent No. 1 ..........
CORAM: P. R. BORA, J.
DATE : 22TH JUNE, 2017.
Per Court :
1.
The respondents-orig. claimants are duly served. 2.
For the reasons stated in the application, which according to me are just and sufficient. The delay of 184 days caused in filing the appeal by the acquiring body is condoned. The appeal be registered in accordance with law.
3.
Civil Application stands disposed of.
4.
On registration of the appeal, issue notice to the respondents. The learned counsel appearing for the original claimant waives service for them in appeal. AGP appears for the State authorities. Service complete.
5.
List the matter for admission after four weeks. 6.
Call Record & Proceedings.
[ P. R. BORA, J. ] ggp