← Library
Bombay High CourtCA/12013/2018disposed offdismissed for default

The Oriental Insurance Company Ltd. Thr Its Branch Manager, Dhule v. Anit Ulhasrao Chavne And ORS

2019-03-27Hon'Ble Shri Justice Sunil K. Kotwal3 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 904 CIVIL APPLICATION NO.12013 OF 2018 IN FAST/25692/2018 THE ORIENTAL INSURANCE COMPANY LTD. THR. ITS BRANCH MANAGER

VERSUS

ANIT ULHASRAO CHAVNE AND ORS.

...

Advocate for Applicant : MR. R. F. Totala Advocate for Respondent No.1 :Mr.Deshpande Chaitanya C. Advocate for Respondent No.3 : Mr.M. S. Sonawane Advocate for respondent No. 4 : Mr. S.N. Boinwar h/f Mr.S.N.Pagare ...

CORAM : SUNIL K.KOTWAL, J.

DATE : 27th MARCH, 2019 O R D E R :

This application is filed by Original Appellant for condonation of delay of 66 days in filing appeal.

2.

Learned counsel for claimant opposes this application.

3.

However, considering the period of delay and reasons assigned for the delay, I am inclined to

ca12013.18 condone the delay.

4.

Application is allowed and the delay of 66 days caused in filing of appeal is condoned.

5.

Application is disposed in terms of prayer clause 'B'. The First Appeal be registered.

6.

Issue notices to respondents.

7.

Mr. C.R. Deshpande, learned counsel waives service of notice for respondent no. 1.

8.

Record and proceeding be called.

9.

Mr. S.R. Pagare, learned counsel waives service of notice for respondent no. 4.

10.

Leave is granted to correct the first name of respondent No. 1 as Anil instead of Anit, as the

ca12013.18 learned counsel for claimant submits; that the corrected first name of the respondent No. 1 is Anil. 11.

Appeal memo be amended accordingly.

12.

Stand over to 8.7.2019.

[SUNIL K.KOTWAL, J.] mahajansb/