Executive Engineer, Latur Medium Project Div. Latur Now Under The G.M.I.D.C Aurangabad And ANR v. Kishan Eknath Haridas
1 987-CA-12939-17-D
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 12939 OF 2017 IN FAST/26667/2017 Executive Engineer, Latur Medium Project Division Latur Now under the GMIDC Aurangabad.
....Applicant
Versus
Vasantrao Haribhau Kulkarni
...Respondent
...
Mr. S. S. Sangle, Advocate for applicant.
Mr. R. D. Sanap, Advocate for respondents.
...
WITH CA/12941/2017 IN FAST/26728/2017 WITH CA/12943/2017 IN FAST/26745/2017 WITH CA/12945/2017 IN FAST/26733/2017 WITH CA/12947/2017 IN FAST/26718/2017 WITH CA/12949/2017 IN FAST/26749/2017 WITH CA/12951/2017 IN FAST/26755/2017 WITH CA/12953/2017 IN FAST/26722/2017 WITH CA/12955/2017 IN FAST/26738/2017 WITH CA/12958/2017 IN FAST/26714/2017 WITH CA/12960/2017 IN FAST/26725/2017 ...
CORAM : SUNIL P. DESHMUKH, J.
DATED : 13th MARCH, 2018.
Order :- 1.
Issue notice to respondents, returnable on 10th April, 2018. 2.
Mr. Sanap, learned counsel waives service of notice on behalf of all respondents.
3.
Heard learned counsel for parties by consent. 4.
Learned counsel for applicants points out contents of the applications and submits that there is no element of deliberation or negligence in approaching the court. He submits that applicants could not move earlier for the reasons as are appearing in applications. 5.
Mr. Sanap, learned counsel though purports to resist applications for condonation of delay, however, he is not in a position to challenge veracity of the contents of applications and reasons thereunder. 6.
In view of aforesaid, the applications are allowed in terms of prayer clause "B" and stand disposed of.
[ SUNIL P. DESHMUKH ] JUDGE MTK.