Shrikant Bapurao Wadekar v. The State Of Maharashtra And Others
{1} 62-WP-12840-18
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO. 12840 OF 2018 Shrikant Bapurao Wadekar
...Petitioner
Versus
The State of Maharashtra and Ors.
...Respondents
Mr A.D. Gadekar, Advocate for Petitioner Mr. P.S. Patil, Additional Government Pleader for Respondent Nos. 1 to 3 Mr K.S. Solanke, Advocate for Respondent No. 4 CORAM : S.V. GANGAPURWALA AND A.M. DHAVALE, JJ.
DATE: 23rd JANUARY, 2019 ORAL ORDER :
1.
The learned Counsel for the petitioner submits that the petitioner has retired on 30.06.2008. He seeks benefit of the Government Resolution dated 30th October, 2009. The issue is no longer res integra. It has been held by this Court in case of Smt. Savitribai Narsayya Guddapa Vs. The State of Maharashtra and Ors. reported in 2014 (6) ALL MR 175 that those who retired in between 01.01.2006 to 26.02.2009, will also be entitled for the benefit of the said Government Resolution.
2.
In light of the above, the respondent/State shall consider the case of the petitioner for payment of revised pension as per the Government Resolution dated 30th October, 2009 after verifying the factual matrix. The petitioner may submit such representation. If such representation is submitted, the same shall be decided as per the
{2} 62-WP-12840-18 Judgment referred to above within a period of four months. 3.
The writ petition is accordingly disposed of. No costs. ( A.M. DHAVALE, J. ) ( S.V. GANGAPURWALA, J. ) mta