M/S Shinde And Sons, Through It S Partner Satish Budhajirao Shinde v. Deputy Chief Engineer (Construction), Central Railway, Private Road, Near R.B. Mill, Pune And Other
40-ARB-12-2018.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD ARBITRATION APPLICATION NO. 12 OF 2018 M/S SHINDE AND SONS, THROUGH ITS PARTNER SATISH S/O BUDHAJIRAO SHINDE
VERSUS
DEPUTY CHIEF ENGINEER (CONSTRUCTION), CENTRAL RAILWAY, PRIVATE ROAD, NEAR R.B. MILL, PUNE AND OTHERS ......
Advocate for Applicants : Mr. Thigale Girish K. (Naik) Advocate for Respondent No. 5 : Mr. M. N. Navandar .....
CORAM : V. K. JADHAV, J.
DATED : 25TH JANUARY, 2021 PER COURT :- 1.
By consent this Court has passed the order dated 11.02.2020 and the Hon'ble Judge P. B. Gaikwad (retired) is appointed as Arbitrator. However, the matter is kept pending for requesting the Hon'ble Justice P. B. Gaikwad (Retired) to forward the disclosure statement if he consents to accept the assignment.
2.
As per the office note, the said disclosure statement, as provided under Section 11 sub-section 8, has now been vre/-
40-ARB-12-2018.odt received and the said disclosure is the part of this Writ Petition.
3.
In view of the same, nothing survives in this petition for consideration. The Arbitration Application is accordingly disposed off.
4.
The proceeding charges of Rs.5,000/- (Rupees Five thousand only) shall be deposited by the applicant within two weeks.
( V. K. JADHAV, J. ) vre/-