← Library
Bombay High CourtCA/4030/2019disposed off

Executive Engineer, Medium Project Division, Latur v. The State Of Maharashtra And ANR

2022-04-01Hon'Ble Shri Justice Shrikant D. Kulkarni2 pages

930-ca.4028.19 ors.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY,

BENCH AT AURANGABAD.

927 CIVIL APPLICATION NO. 4028 OF 2019 IN FA/2466/2019 WITH CA/4030/2019 IN FA/2467/2019 WITH CA/4036/2019 IN FA/2469/2019 WITH CA/4034/2019 IN FA/2468/2019 EXECUTIVE ENGINEER, MEDIUM PROJECT DIVISION, LATUR

VERSUS

THE STATE OF MAHARASHTRA AND ANOTHER ...

Mr. Vinesh C. Solshe, Advocate for Applicant. Mr. P. M. Kulkarni, AGP for Respondent No.1/State. Mr. Hanmant V. Patil, Advocate for Respondent No.2. ...

CORAM :

SHRIKANT D. KULKARNI, J.

DATE :

01st April, 2022.

P.C.:

.

These are the applications for stay moved by the applicant/acquiring body.

Heard Mr. Solshe, learned counsel for applicant/acquiring body, Mr. P. M. Kulkarni, learned AGP for respondent No.1 and Mr. Patil, learned counsel for original claimant.

It is revealed during the course of argument that the applicant/acquiring body has deposited the entire amount of compensation under the impugned award in this Court and complied the earlier order of interim stay passed by this Court. As such, the

930-ca.4028.19 ors.odt interim stay granted by this Court needs to be made absolute. Hence, the following order is passed:

O R D E R

I.

The applications are hereby allowed in terms of prayer clauses (A) and (B).

II.

Inform to the concerned Reference Court/ Executing Court accordingly.

III.

The civil applications are accordingly disposed of. [ SHRIKANT D. KULKARNI, J. ] nga