Dnyanoba Rangrao Somwanshi And ORS v. The State Of Maharashtra And ORS
1 24-CA 13469-2018.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 13469 OF 2018 IN FAST/26678/2018 Dnyanoba Rangrao Somwanshi and others .. Applicants
Versus
The State of Maharashtra and others .. Respondents Mr. Vijay B. Patil, Advocate for the Applicants. Mr. S. S. Dande, AGP for Respondent Nos. 1 and 2. Mr. Sham B. Patil, Advocate for Respondent No. 3. CORAM : KISHORE C. SANT, J.
DATED : 06th NOVEMBER, 2023.
P. C. :- .
Heard learned advocates for the parties.
2.
This application is filed by the original claimants for condonation of delay caused in filing first appeal. The first appeal is filed for enhancement of the amount of compensation challenging the judgment and award passed by the learned Reference Court to the limited extent. 3.
Considering that, the applicants are claimants and they are seeking enhancement in the amount for their land, this Court finds that the application needs to be allowed.
4.
For the reasons recorded in the civil application, civil application
2 24-CA 13469-2018.odt is allowed. Delay stands condoned.
5.
Office to register the first appeal.
6.
The civil application is disposed off.
( KISHORE C. SANT, J. ) P.S.B.