The Executive Engineer, Irrigation Project Concrete, (Majbutikaran) Division, Omerga v. Anil Sidram Shinde And ORS

2017-04-13Hon'Ble Shri Justice V.K. Jadhav2 pages

14-ca.13185.16 delay.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY,

BENCH AT AURANGABAD.

14 CIVIL APPLICATION NO. 13185 OF 2016 IN FAST/27250/2016 WITH CA/13187/2016 IN FAST/27828/2016 WITH CA/13190/2016 IN FAST/27590/2016 WITH CA/13192/2016 IN FAST/27587/2016 WITH CA/13194/2016 IN FAST/27584/2016 WITH CA/13196/2016 IN FAST/27581/2016 WITH CA/13198/2016 IN FAST/27577/2016 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT CONCRETE, (MAJBUTIKARAN) DIVISION, OMERGA

VERSUS

ANIL SIDRAM SHINDE AND OTHERS ...

Advocate for Applicant : Mr. Ruturaj C. Patil. Advocate for Respondents / Claimants : Mr. L. C. Patil. AGP for Respondents State / SLAO : Mr.A.M.Phule ...

CORAM :

V. K. JADHAV, J.

DATE :

13th April, 2017.

P.C.:

.

Heard both the sides.

The learned counsel for the Applicant / acquiring body submits that old division of the Appellant has been closed after the judgment and award passed by the Reference Court and the entire files came to be transferred to the new division and as such, delay has been occurred in preferring the appeals.

The learned counsel for Respondents / original Claimants submits that the Applicant has not explained the delay satisfactorily.

14-ca.13185.16 delay.odt In view of the submissions made on behalf of the acquiring body and for the reasons stated in the application, the delay of 1180 days caused in filing the appeals is hereby condoned. Civil applications for condonation of delay are allowed and accordingly disposed of. In appeals, heard. Issue notice to the Respondents, returnable on 15th June, 2017. The learned counsel appearing for Respondents / Claimants and the learned AGP for Respondents / State and SLAO waive the service of notice for the respective Respondents. Record and proceedings be called for.

[ V. K. JADHAV, J. ] ndm