IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 933 CIVIL APPLICATION NO. 7253 OF 2022 IN FAST/26048/2020 The Ex. Engineer, Osmanabad Medium Project Div. Osmanabad and Ors.

....Applicants

VERSUS

Kamal Trimbak Gud (died) Thr Lrs Ratnaprabha and Ors.

.....Respondents .....

Mr. Tambe Rahul A., Advocate for Applicants Mr. M. K. Jadhav h/f Mr. Abhijit More, Advocate for Respondent Nos.1 to 6 .....

CORAM

:

NEERAJ P. DHOTE, J.

DATE :

11.03.2025 PER COURT :

1.

This is an Application for condonation of 300 days delay caused in preferring the First Appeal against the Judgment and Award dated 23/01/2019, passed by the Reference Court, in Land Acquisition Reference No.485/2016.

2.

Heard the learned Advocate for the Applicants - Acquiring Body and the learned Advocate for Respondent Nos.1 to 6. 3.

It is submitted by the learned Advocate for the Applicants - Acquiring Body that, suffcient reasons are mentioned in the Application for condonation of delay and the Appeal is to the extent of interest amount.

4.

The Application is opposed by the learned Advocate for Respondent Nos.1 to 6.

933-CA-7253-2022.odt 5.

On going through the Application, it is clear that, suffcient reasons are mentioned in the Application for condonation of delay. Hence, the Application is allowed in terms of prayer clause - [B]. The Offce to register the Appeal.

6.

Application is disposed of accordingly.

[NEERAJ P. DHOTE, J.] Sameer/March-2025 Signed by: Md. Sameer Q.

Designation: PA To Honourable Judge Date: 13/03/2025 11:21:11