Executive Engineer Medium Irrigation Project Dhule v. Makan Bhaga Girase And Others

2019-08-30Hon'Ble Smt. Justice Vibha Kankanwadi2 pages

1010-ca-8596-15 (delay).doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 1010 CIVIL APPLICATION NO.8596 OF 2015 IN FAST/26981/2014 WITH CA/8606/2015 IN FAST/26995/2014 WITH CA/8608/2015 IN FAST/26999/2014 EXECUTIVE ENGINEER MEDIUM IRRIGATION PROJECT DHULE

VERSUS

SAHEBRAO BANDU GIRASE AND THERS ...

Advocate for Applicant : Ms. Jadhav Vaishali D. AGP for Respondents/State : Mr. R.B. Bagul Advocate for Respondent No.1 : Mr. A.B. Kale ...

CORAM : SMT. VIBHA KANKANWADI, J.

DATE : 30th AUGUST, 2019 ORDER :

.

Present applications have been filed by the acquiring body for getting the delay of 418 days condoned in filing first appeals. The acquiring body intends to challenge the judgment and award passed by the reference Court. Under such circumstance, though the application has been strongly opposed by the original claimants, for the reasons mentioned in the applications, the delay stands condoned. 2.

Civil Applications stand allowed and disposed of accordingly.

1010-ca-8596-15 (delay).doc 3.

Registry to verify and register the first appeals and place them for further consideration on 13.11.2019.

(SMT. VIBHA KANKANWADI, J.) SCM