The New India Assurance Company Ltd., Thr Its Authorized Signatory Aurangabad v. Jijabai Ukhadu Sherkar And ORS
{1} ca11743-17 drp
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 11743 OF 2017 IN FIRST APPEAL STAMP NO.29645 OF 2017 The New India Assurance Co.Ltd., APPLICANT
VERSUS
Jijabai Ukhadu Sherkar and Others RESPONDENTS .......
Mr. M. M. Ambhore, Advocate for the applicant Mr. M. K. Bhosale, Advocate for respondents No.1 to 5 .......
[CORAM : SUNIL P. DESHMUKH, J.] DATE : 16 th MARCH, 2018 ORDER :
1.
Heard learned advocates for the parties.
2.
Learned advocate for applicant - insurer states that deposit of the amount could not be made pursuant to order dated 19th September, 2017 within stipulated period on account of various reasons. However, the amount is now ready and cheque has also been issued. In the circumstances, requests for extension of time to deposit the amount under order dated 19th September, 2017.
3.
Learned advocate for the respondents has no objection for
{2} ca11743-17 extension of time for making deposit of the amount. 4.
In view of the same, period for making deposit pursuant to order dated 19th September, 2017 is extended up to 28th March, 2018. Office to accept the payment, if deposited by 28th March, 2018.
[SUNIL P. DESHMUKH, J.] drp/ca11743-17