← Library
Bombay High CourtCA/1077/2014admittedallowedgrantedrule absolute

The Executive Engineer(Construction) Central Railway Division Latur v. Subhash Kishanrao Veer And Another

2016-02-12Hon'Ble Shri Justice T.V. Nalawade4 pages

1 C.A. 1077....2014 IN F.A. St. 29937.2013.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD

4. CA/1077/2014 FAST/29937/2013 THE EXECUTIVE ENGINEER(CONSTRUCTION) CENTRAL RAILWAY DIVISION, LATUR SUBHASH KISHANRAO VEER AND ANOTHER CA/1058/2014 FAST/30024/2013 (CONSTRUCTION) CENTRAL RAILWAY BHIMABAI NAGNATH NARHARE, L.R. GOVIND NAGNATH AND ANR.

CA/1060/2014 FAST/30031/2013 SIMINTABAI LAXMAN MANE AND ANOTHER CA/1062/2014 FAST/30006/2013 VITHAL VENKATI AUSKARAND ANOTHER

2 C.A. 1077....2014 IN F.A. St. 29937.2013.odt CA/106342014 FAST/30036/2013 KALYAN BHAURAO MULE AND ANOTHER CA/1066/2014 FAST/30027/2013 VITHALRAO RAMRAO VEER AND ANOTHER CA/1068/2014 FAST/30019/2013 TULSIRAM NARSAPPA CHAME AND ANOTHER CA/1070/2014 FAST/30015/2013 SHIVRAM JAYWANTA KUMBHAR AND ANOTHER CA/1072/2014 FAST/30011/2013

3 C.A. 1077....2014 IN F.A. St. 29937.2013.odt RAJKUMAR BABUWAN PATIL AND ANOTHER CA/1074/2014 FAST/30003/2013 ABHANG NARSING VEER AND ANOTHER .....

Mr. D.V.Soman, Advocate for Applicant.

Mr. K.N.Lokhande, A.G.P. for Resp. - State.

.....

CORAM : T.V.NALAWADE, J.

DATE : 12th FEBRUARY, 2016 ORAL ORDER :- .

Heard learned counsel for the applicant.

2.

Seen the Judgment and Award.

3.

Stay needs to be granted on depositing the entire amount of compensation within 12 weeks from today.

4.

In the aforesaid circumstances, Civil applications are allowed. If the amount is not deposited

4 C.A. 1077....2014 IN F.A. St. 29937.2013.odt within stipulated time, it is to be presumed that there is no stay granted.

5.

Call record and proceedings.

[T.V.NALAWADE, J.] KNP/C.A. 1077....2014 IN F.A. St. 29937.2013.odt