The Executive Engineer, Nimna Dudhana Project Division, Sailu And Others v. Bhagabai Premrao Mhaske
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CA/14031/2015 IN FAST/29245/2015 WITH CA/14033/2015 IN FAST/29258/2015 WITH CA/14035/2015 IN FAST/29248/2015 WITH CA/14039/2015 IN FAST/29241/2015 WITH CA/14042/2015 IN FAST/29251/2015 WITH CA/14047/2015 IN FAST/29530/2015 THE EXECUTIVE ENGINEER, NIMNA DUDHANA PROJECT DIVISION, SAILU AND OTHERS
VERSUS
DEVIDAS APPARAO BAHEKAR ...
Advocate for Applicants : Mr. Patil Ruturaj C. ...
CORAM : P.R. BORA, J.
Dated: April 01, 2016 ...
PER COURT :- 1) By order dated 23rd October, 2015, ad interim stay to the impugned judgment and Award was granted by this Court on condition that the applicants/appellants shall deposit entire amount under the Award by the Reference Court within a period of ten weeks from the date of said order. BDV
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD (2) 2) The learned Counsel for the applicants/appellants submits that for genuine reasons, the appellant could not deposit the amount of compensation within the stipulated time. The learned counsel further submits that now, he has received from the acquiring body the cheque for the entire amount and intends to deposit the same in the Registry of this Court.
3) In view of the submission so made, time stands extended for depositing the amount of compensation. The Registry is directed to accept the cheque towards the amount of compensation as directed by this Court.
4) Civil Applications stand disposed of.
( P.R. BORA, J. ) ...
BDV