← Library
Bombay High CourtCA/11089/2024admittedallowedgrantedrule absolute

The New India Assurance Company Ltd Through Its Branch Manager v. Sangita Bhausaheb Prabhane And ORS

2025-03-21Hon'Ble Shri Justice S. G. Chapalgaonkar2 pages

2025:BHC-AUG:8785 (1) 61-ca-11089-2024-delay.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 11089 OF 2024 IN FAST/26600/2024 THE NEW INDIA ASSURANCE COMPANY LTD THROUGH ITS BRANCH MANAGER

VERSUS

SANGITA BHAUSAHEB PRABHANE AND ORS ...

Mrs. Anagha Rotte, Advocate for Applicant.

Mr. D. A. Bide, Advocate for Respondent Nos.1 to 4. ...

CORAM : S. G. CHAPALGAONKAR, J.

DATED : 21st MARCH, 2025.

P.C.:- 1.

The learned Advocate for the applicant seeks permission to delete respondent no.6 as no relief is claimed in this Appeal. 2.

Permission is granted at the risk of applicant. Amendment to be carried out forthwith.

3.

Heard learend Advocates appearing for respective parties. 4.

By this application, applicant seeks to condone delay of 30 days caused in filing Appeal.

5.

Considering the reasons as stated in the application, delay appears to be on account of administrative exigency. The applicant has not derived any advantage by making such delay. Hence, following order:

ORDER

a.

Civil Application is allowed.

b.

Dealy of 30 days caused in filing Appeal is hereby condoned.

(2) 61-ca-11089-2024-delay.odt c.

Appeal be registered.

d.

On registration of Appeal, issue notice to the respondents, returnable on 02.05.2025.

e.

Call for Record and Proceeding.

f.

Parties are put to the notice that appeal may be heard finally at the stage of admission, if time permits.

(S. G. CHAPALGAONKAR) JUDGE Devendra/March-2025