The Executive Engineer Dept. Of Seena Kolegaon Project Paranda v. Habbib Hasan Sayyad And ORS
2025:BHC-AUG:11167 (1) 62-ca-11493-2024.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 11493 OF 2024 IN FAST/26628/2024 THE EXECUTIVE ENGINEER DEPT. OF SEENA KOLEGAON PROJECT PARANDA
VERSUS
HABBIB HASAN SAYYAD AND ORS ...
Mr. Madhav N. Kalyane h/f Mr. Gulab Balbhim Rajale, Advocate for Applicant.
Mr. S. P. Joshi, AGP for Respondents-State.
...
CORAM : S. G. CHAPALGAONKAR, J.
DATED : 17th APRIL, 2025.
P.C.:- 1.
Heard learned Advocates appearing for respective parties. 2.
By this application, applicant seeks to condone delay of 1922 days caused in filing appeal against award passed by Reference Court.
3.
Perused reasons as stated in application. The delay appears to have been caused on account of administrative exigency. The applicant has not derived any advantage by making such delay. Hence, sufficient cause is made out to condone delay. Hence, following order:
ORDER
a.
Civil Application is allowed.
b.
Delay of 1922 days caused in filing appeal is hereby condoned.
c.
Appeal be registered subject to removal of office objections. (S. G. CHAPALGAONKAR) JUDGE Devendra/April-2025