Executive Engineer, Medium Project, Omerga v. Balbhim Govind Jadhav And Others
919-ca.15997.13.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
BENCH AT AURANGABAD.
919 CIVIL APPLICATION NO. 15997 OF 2013 IN FAST/30429/2013 EXECUTIVE ENGINEER, MEDIUM PROJECT, OMERGA
VERSUS
BALBHIM GOVIND JADHAV AND OTHERS ...
Advocate for Applicant : Mrs. Sunita Shelke.
Advocate for Claimants : Mr. Pravin B. Rakhunde. AGP for Respondent Nos.2 & 3: Mr. S. P. Deshmukh. ...
CORAM :
SHRIKANT D. KULKARNI, J.
DATE :
07th April, 2022.
P.C.:
.
It is an application for condonation of delay moved by the applicant/acquiring body.
Heard Ms. Sunita Shelke, learned counsel for the applicant, Mr.Rakhunde, learned counsel for claimants and Mr. Deshmukh, learned AGP for respondent Nos.2 and 3.
There seems to be delay of 577 days in preferring the first appeal. However, by looking to the nature of dispute and for the reasons stated in the application for condonation of delay, paragraphs 8 to 10, the delay needs to be condoned. Hence, the following order is passed:
919-ca.15997.13.odt
O R D E R
I.
The application is hereby allowed in terms of prayer clause (B).
II.
The Registry to make scrutiny of the appeal as per the procedure and it be numbered and placed before the Court for admission.
III.
The civil application is accordingly disposed of. [ SHRIKANT D. KULKARNI, J. ] nga