The Ex. Engineer, Minor Irrigation Pwd Div. Osmanabad And ANR v. Rameshwar Krishna Todkari And ANR
23.1.CA.12344.17.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 23.1 CIVIL APPLICATION NO.12344 OF 2017 IN FAST/31735/2017 THE EX. ENGINEER, MINOR IRRIGATION PWD DIV. OSMANABAD AND ANR
VERSUS
RAMESHWAR KRISHNA TODKARI AND ANR ...
Advocate for Applicant no.1 : Mr. Karlekar Sujeet G. AGP for applicant no. 2: Mr. R.B. Bagul Advocate for Respondent Nos. 1 and 2 : Mr. L.C. Patil ...
CORAM
: MANGESH S. PATIL, J.
DATE : .14.11.2019 PER COURT :
Heard both the sides. There is a delay of 1450 days in preferring the appeal by the acquiring body challenging the judgment and order passed by the reference court under Section 18 of the Land Acquisition Act.
2.
True it is that the delay is enormous, however, considering the grounds mentioned in the application and taking into account the fact that even the claimants are impugning the same judgment and award, the delay is condoned.
(MANGESH S. PATIL, J.) habeeb 1/1