IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (1) CA NO.12526/2014gr 926 CIVIL APPLICATION NO. 12526 OF 2014 IN FAST/30647/2014 WITH CA/12528/2014 IN FAST/30650/2014 WITH CA/12534/2014 IN FAST/30656/2014 WITH CA/12536/2014 IN FAST/30659/2014 WITH CA/12538/2014 IN FAST/30662/2014 THE EXECUTIVE ENGINEER DHULE MEDIUM PROJECT DHULE

VERSUS

NARAYANSING TODARSING GIRASE AND OTHERS ...

Advocate for Applicant :Mr. Pawar Ajay D.

AGP for Respondent State:Mr.S.N.Morampalle Mr.Kale Ajeet B., Adv for R/1 and 3.

...

CORAM : P.R. BORA, J.

Dated: July 22, 2016 ...

PER COURT :- 1.

Delay of 671 days has occurred in filing the appeals by the acquiring body. Learned Counsel for the appellants submits that in seeking procedural compliances and in obtaining sanctions at different levels, time was consumed and that is the reason delay of 671 days has occurred in filing the appeals. Learned Counsel appearing for the claimants has opposed the applications for condonation of delay stating that the reasons are not just and sufficient.

AGP/-

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (2) CA NO.12526/2014gr 2.

After having considered the submissions made by the parties and on going through the reasons stated in the applications, I am inclined to allow the present applications for condonation of delay since delay has been properly justified. The applications are allowed. Delay is condoned. Appeals be registered in accordance with law. ( P.R. BORA, J. ) ...

AGP/-