Bombay High CourtWP/12047/2018disposed offdismissed for default

Balu Sahebrao Bankar And Others v. The Executive Engineer Irrigation Department Godawari Project 2 And Another

2019-02-22Hon'Ble Shri Justice S V Gangapurwala,Hon'Ble Shri Justice Arun M. Dhavale1 pages

1 wp 12047.18

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD WRIT PETITION NO. 12047 OF 2018 Balu Sahebrao Bankar and others .. Petitioners

Versus

The Executive Engineer Irrigation Department, Godawari Project 2 and another .. Respondents Shri Vishal A. Bagal, Advocate for Petitioners. Shri S. G. Karlekar, A.G.P. for the Respondent No. 2. CORAM : S. V. GANGAPURWALA AND A. M. DHAVALE, JJ.

DATE : 22ND FEBRUARY, 2019.

ORDER :

.

The affidavit is filed by the Tahsildar (Revenue) saying that the representation of the petitioner would be decided within a period of six (06) months.

2.

In view of the above, the writ petition stands disposed of. No costs.