Executive Engineer, Lower Dudhna Project Division, Sailu Now Jalna Irrigation Div., Jalna And ORS v. Abasaheb Bapurao Kharad Died Thr Lrs Zugarabai And ORS
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 921 CIVIL APPLICATION NO. 15541 OF 2016 IN FAST/31931/2016 EXECUTIVE ENGINEER, LOWER DUDHNA PROJECT DIVISION, SAILU NOW JALNA IRRIGATION DIVISION
VERSUS
ABASAHEB BAPURAO KHARAD DIED THR LRS ZUGARABAI AND ORS ...
Advocate for Applicant : Mr.Surwase B.R.
R/1 To 4 Served ...
CORAM : P.R. BORA, J.
Dated: July 11, 2017 ...
PER COURT :- 1.
Though the respondents are duly served, have not entered their appearance in the matter.
2.
Delay of 345 days has occurred in filing the present appeal by the acquiring body. The reasons for occurrence of delay are explained in paragraph no.6 of the application. The reasons which are assigned are probable reasons and cannot be outrightly rejected. I am, therefore, inclined to allow the application so that the appeal can be heard on merits. Hence, the following order:
ORDER
1.
The Application is allowed. The delay caused in filing the appeal is condoned. Civil Application stands disposed of. 2.
The Appeal be registered in accordance with law. ( P.R. BORA, J. ) ...
agp/-