Bombay High CourtCA/948/2014admittedallowedgrantedrule absolute
The Executive Engineer, Minor Irrigation Division, Jalna v. Pralhad Bapurao Borkar And Others
2015-02-02Hon'Ble Shri Justice M.T. Joshi1 pages
ca948-14
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 948 OF 2014 IN FIRST APPEAL ST. NO. 32124 OF 2013 (The Executive Engineer, Minor Irrigation Division, jalna Vs. Pralhad Bapurao Borkar and others) ---- Mr. S.C. Arora, Advocate for the applicant Mr. A.B. Kale, Advocate for respondent No. 1. ---- CORAM : M.T. JOSHI, J.
DATE : 02/02/2015 ORAL ORDER :
1.
Heard both sides.
2.
Mr. Arora, learned counsel for the applicant submits that for want of budgetary provision/sanction from the Government, the delay for filing first appeal has occurred. Since the sufficient reason is made out in the application, the delay is condoned. The application is allowed accordingly and disposed of. [M.T. JOSHI] JUDGE npj/ca948-14