The State Of Maharashtra And ANR v. Manchak Vithal Dongre
943.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 943 CIVIL APPLICATION NO. 172 OF 2011 IN FAST/34116/2010 WITHCA/174/2011 IN FAST/34126/2010 WITH CA/176/2011 IN FAST/34105/2010 WITH CA/178/2011 IN FAST/34120/2010 WITH CA/180/2011 IN FAST/34135/2010 WITH CA/182/2011 IN FAST/34129/2010 WITH CA/184/2011 IN FAST/34139/2010 WITH CA/186/2011 IN FAST/34080/2010 THE STATE OF MAHARASHTRA AND ANR
VERSUS
ARJUN BALAJI LAHANE AND ORS ...
Advocate for Applicants :Mr. S. P. Sonpawale, AGP Advocate for non applicants : Mr. B. R. Kedar
CORAM
: A. M. BADAR, J.
DATE :
09th December, 2015 PER COURT :
1.
These are applications for condonation of delay of 234 days in filing appeals under section 54 of the Land Acquisition Act.
2.
Heard learned AGP as well as Mr. Kedar, learned counsel appearing for non applicants. Perused application. 3.
It is seen that the delay is occasioned because of the fact that conscious decision was required to be taken at different levels and the same is properly explained. Hence, for the reasons stated, delay is condoned. Civil applications are disposed of accordingly. ( A. M. BADAR, J. ) JPC 1/1