Dnyanoba Rambhau Kadam v. Executive Engineer, Nimna Dhudhana Project Selu And ORS
965-CA-12749-2017.odt (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 965 CIVIL APPLICATION NO. 12749 OF 2017 IN FAST/37630/2016 DNYANOBA RAMBHAU KADAM
VERSUS
EXECUTIVE ENGINEER, NIMNA DUDHANA PROJECT SELU AND ORS ...
Advocate for Applicant : Mr. K.M. More h/f Mr. S.S. Randive AGP for Respondents : Mr. P.M. Kulkarni Advocate for Respondent No.1 : Mr. B.R. Surwase ...
CORAM : P.R. BORA, J.
DATED : 24th OCTOBER, 2018.
PER COURT:- .
Heard the learned counsel for the applicant and the learned counsel appearing for the acquiring body and the learned AGP appearing for respondent-State.
2.
In view of the submissions made, the following order is passed:
ORDER
i) The applicant is permitted to withdraw 60% of the deposited amount on submitting an undertaking to the satisfaction of the Registrar of this Court.
ii) Balance amount be invested in Fixed Deposit Receipt in any nationalized bank,
965-CA-12749-2017.odt (2) initially for a period of one year and if so required, till disposal of the appeal.
iii) The Civil Application stands disposed of.
(P.R. BORA, J.) Mujaheed//