← Library
Bombay High CourtCA/12120/2014admittedallowedgrantedrule absolute

The Managing Director Indapur Co-Operative Sugar Factory Ltd. Now Known As Karmyogi Shankarrao Pati v. Vimal Sarjerao Narwade And Others

2015-06-12Hon'Ble Shri Justice T.V. Nalawade1 pages

IN THE HIGH COURT AT BOMBAY

APPELLATE SIDE, BENCH AT AURANGABAD

26. CA/12120/2014 In FAST/31871/2014 WITH CA/12121/2014 In FAST/31871/2014 THE MANAGING DIRECTOR INDAPUR CO-OPERATIVE SUGAR FACTORY LTD. V/S VIMAL SARJERAO NARWADE AND OTHERS Mr. Y.S. Choudhari, Advocate for applicant.

Mr. D.R. Jaybhar, Advocate for respondent Nos. 1 to 4. CORAM : T.V. NALAWADE, J.

DATED : 12th June, 2015.

ORDER :

1.

The application is filed for condonation of delay of 33 days caused in filing appeal against judgment and order given by the Commissioner appointed under the Workmen's Compensation Act. In view of the contents of the application, the application is allowed. The delay is condoned. 2.

Notice in appeal. Learned counsel Shri. Jaybhar waives notice for original claimants/respondents. 3.

Call record and proceedings. Both the sides agree to argue the matter for final disposal on 3.7.2015. Stand over to 3.7.2015.

[ T.V. NALAWADE, J. ] ssc/