Suryakant Digambar Gavhane v. The State Of Maharashtra Through Secretary And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 30 WRIT PETITION NO.12635 OF 2023 CHANDRASEN DAGDU SHINDE
VERSUS
THE STATE OF MAHARASHTRA THROUGH THE SECRETARY AND OTHERS AND 36 WRIT PETITION NO.12647 OF 2023 SUDHAKAR DAGDU SHINDE
VERSUS
THE STATE OF MAHARASHTRA THROUGH THE SECRETARY AND OTHERS AND 37 WRIT PETITION NO.12648 OF 2023 MARUTI DAGDU SHIDNE
VERSUS
THE STATE OF MAHARASHTRA THROUGH THE SECRETARY AND OTHERS AND 40 WRIT PETITION NO.12655 OF 2023 SURYAKANT DIGAMBAR GAVHANE
VERSUS
THE STATE OF MAHARASHTRA THROUGH SECRETARY AND OTHERS AND 104 WRIT PETITION NO.12819 OF 2023 DAGDU MARUTI SHINDE
VERSUS
THE STATE OF MAHARASHTRA THROUGH THE SECRETARY AND OTHERS ...
Mr. Rajkumar B. Dhaware, Advocate for Petitioners Mr. A V. Deshmukh, Mr. S. K. Tambe, Mr. S. G. Karlekar, AGPs for the Respondents-State
CORAM
: RAVINDRA V. GHUGE & Y. G. KHOBRAGADE, JJ.
DATE : 16th October, 2023 ORDER:
1.
In all these matters, the Petitioners claim to be identically placed. All of them claim to be the owners and possessors of agricultural lands alongwith fruit bearing trees, wells, residential houses, bore wells etc. adjacent to the State Highway No.232. Their grievance is that earlier the width of the road was only 8 to 10 meters in 1971-1972. Now the road has become a State Highway and the width is around 30 meters.
2.
By now, it is well settled that a public project should not be stalled. If the Petitioners are encroachers, the encroachments have to be removed. However, if they have a right and title, evidence through documents pertaining to such lands which are being utilized for the State Highway, will have to be produced and if the record reveals that their lands are being acquired for the State Highway, they would be entitled for compensation under the The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
3.
In view of the above, these Petitions are disposed off with the following directions :-
[a] Let the Executive Engineer, PWD of all the respective Divisions complete the exercise of issuing notices to all these Petitioners (some of them have already been issued with such notices), for removal of encroachments.
[b] All those who have received the notices and those who would receive such notices, shall tender their written replies alongwith authenticated documents showing their title and ownership over the property, within 15 days from today or within 15 days from the receipt of the notices which would now be issued. [c] The Respondents would be at liberty to carry out a joint measurement of the lands in order to assess the size of the lands, which are being utilized for the public project. [d] If the record reveals and the Petitioners are unable to establish their ownership over the said lands, portions of which would be utilized for the widening of the road, they would be informed to remove the encroachments voluntarily within a particular time, failing which, the Respondents can initiate steps for removal of such encroachments and charge them for such exercise. [e] Needless to state, if the Petitioners'
claims are sustained in Law and it is proved that their lands have been acquired, an appropriate proposal shall be forwarded by the Acquiring
Authority to the competent authority and the proceedings under the 2013 Act would be completed within the timeline as is prescribed. In such a situation, the Petitioners will have to relocate themselves so as to make way for the said project. ( Y. G. KHOBRAGADE, J. ) ( RAVINDRA V. GHUGE, J. ) JPChavan