The Maharashtra State Electricity Distribution Company Ltd., Mumbai And Another v. M/S Omshree Agro Tech. Lte., Thro. Director Mahendra Onkar Agrawal
ca788.20 -1-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 938 CIVIL APPLICATION NO.788 OF 2020 IN SAST/32399/2019 THE MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD., MUMBAI AND ANOTHER
VERSUS
M/S OMSHREE AGRO TECH. LTE., THRO. DIRECTOR MAHENDRA ONKAR AGRAWAL .....
Advocate for Applicants : Mr. Salve Avinash R. Advocate for Respondents : Mr. M.S. Kulkarni .....
CORAM : BHARAT P. DESHPANDE, J.
DATED : 25th AUGUST 2022 PER COURT:- 1.
Heard. Mr. Kulkarni appear for respondents.
2.
This is an application for condonation of delay of 16 days caused in filing the second appeal. Considering the grounds mentioned in para 3 of the application, which is considered as sufficient cause, the delay could be condoned. Hence, the following order:-
O R D E R
I.
Civil application stands allowed.
II.
The delay of 16 days caused in filing second appeal is
ca788.20 -2condoned.
III.
Office to register the appeal, if all other office objections are removed.
IV.
Civil application stands disposed of.
(BHARAT P. DESHPANDE, J.) rlj/