ca788.20 -1-

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 938 CIVIL APPLICATION NO.788 OF 2020 IN SAST/32399/2019 THE MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD., MUMBAI AND ANOTHER

VERSUS

M/S OMSHREE AGRO TECH. LTE., THRO. DIRECTOR MAHENDRA ONKAR AGRAWAL .....

Advocate for Applicants : Mr. Salve Avinash R. Advocate for Respondents : Mr. M.S. Kulkarni .....

CORAM : BHARAT P. DESHPANDE, J.

DATED : 25th AUGUST 2022 PER COURT:- 1.

Heard. Mr. Kulkarni appear for respondents.

2.

This is an application for condonation of delay of 16 days caused in filing the second appeal. Considering the grounds mentioned in para 3 of the application, which is considered as sufficient cause, the delay could be condoned. Hence, the following order:-

O R D E R

I.

Civil application stands allowed.

II.

The delay of 16 days caused in filing second appeal is

ca788.20 -2condoned.

III.

Office to register the appeal, if all other office objections are removed.

IV.

Civil application stands disposed of.

(BHARAT P. DESHPANDE, J.) rlj/