Piraji Savalu Thelari Alias Marnar And Others v. The State Of Maharashtra Through Its Principal Secretary And Others
12825.23wp (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 110 WRIT PETITION NO.12825 OF 2023 PIRAJI SAVALU THELARI (MARNAR) AND OTHERS
VERSUS
THE STATE OF MAHARASHTRA THROUGH ITS PRINCIPAL SECRETARY AND OTHERS ....
Mr A. B. Kale, Advocate for Petitioners;
Mr V. M. Kagne, A.G.P. for Respondents/State CORAM : RAVINDRA V. GHUGE AND Y. G. KHOBRAGADE, JJ.
DATE : 17th October, 2023 PER COURT:
1.
This is a second round for the Petitioners, before this Court. In the earlier round, the Petitioners had preferred Writ Petition No.7423/2023. By an order dated 10/07/2023, we had directed that the proposal should be forwarded under the Maharashtra Highways Act, 1955, within 45 days. We were conscious of the fact that 7 months had already lapsed. We had, therefore, directed that the entire exercise of concluding acquisition proceeding be completed within the prescribed timeline.
12825.23wp (2) 2.
The learned Advocate for the Petitioners submits that, since no timeline is prescribed under the Maharashtra Highways Act, the Respondents are now ignoring the matter. 3.
The learned A.G.P. submits that, Respondent No.2 would complete the said proceeding within the timeline, as may be directed by this Court.
4.
In view of the above, this Writ Petition is disposed off, with a direction to Respondent No.2/District Collector, Dhule, to conclude the proceeding within 180 days from today. Thereafter, payment of compensation, if any, shall be done within 60 days.
(Y. G. KHOBRAGADE, J.) (RAVINDRA V. GHUGE, J.) sjk