IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 944 WRIT PETITION NO. 13487 OF 2025 Nipuna Developers Through Its Partner Vinodkumar Vithalrao Shriramwar

VERSUS

The State Of Maharashtra And Others ......

Mr. P.R. Katneshwarkar, Senior Advocate i/b Mr. Prathamesh Kundalwadikar, Advocate for Petitioner Ms. Saie S. Joshi, AGP for Respondents No.1 to 3 ......

CORAM : SMT. VIBHA KANKANWADI AND HITEN S. VENEGAVKAR, JJ.

DATE : 13 NOVEMBER, 2025 PER COURT :- 1.

Mr. Katneshwarkar, learned Senior Advocate instructed by Mr. Kudalwadikar, learned Advocate for the petitioner, submits that the petitioner has submitted an application dated 07.12.2023 for regularization of Gunthewari to respondent No.3; however, the same has not yet been decided.

2.

Learned AGP waives notice for all respondents and, upon specific instructions from respondent No.3, makes a statement that the said application will be decided within a period of two months. The said statement is accepted as an undertaking.

944-WP-13487-25.odt {2} 3.

We dispose of the writ petition with a direction to respondent No.3 to decide the application submitted by the petitioner on 07.12.2023 within a period of two months from today. [ HITEN S. VENEGAVKAR ] [ SMT. VIBHA KANKANWADI ] JUDGE JUDGE S P Rane