← Library
Bombay High CourtCA/16242/2016admittedallowedgrantedrule absolute

The Executive Engineer, Minor Irrigation Division, Latur Thr Gmidc Aurangabad v. Digambar Vishwanathrao Sangame And ORS

2024-08-30Hon'Ble Shri Justice N. B. Suryawanshi2 pages

2024:BHC-AUG:19875 ca16241-16.doc drp

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 16241 OF 2016 IN FIRST APPEAL STAMP NO.35595 OF 2016 The Executive Engineer, MID, Latur Through GMIDC Aurangabad APPLICANT

VERSUS

Digambar Vishwanathrao Sangame and Others RESPONDENTS .......

Mr. V. P. Kadam, Advocate for, Advocate for the applicant Mr. D. B. Bhange, AGP for respondent - State Mr. Shrikant J. Sonkawade respondents - claimants .......

[CORAM : NITIN B. SURYAWANSHI, J.] DATE : 30 th AUGUST, 2024 ORDER :

1.

Heard.

2.

For the reasons stated in application, delay is condoned. Application is allowed.

[NITIN B. SURYAWANSHI] JUDGE drp/ca16241-16.doc

ca16241-16.doc drp

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 16242 OF 2016 IN FIRST APPEAL STAMP NO.35595 OF 2016 The Executive Engineer, MID, Latur Through GMIDC Aurangabad APPLICANT

VERSUS

Digambar Vishwanathrao Sangame and Others RESPONDENTS .......

Mr. V. P. Kadam, Advocate for, Advocate for the applicant Mr. D. B. Bhange, AGP for respondent - State Mr. Shrikant J. Sonkawade respondents - claimants .......

[CORAM : NITIN B. SURYAWANSHI, J.] DATE : 30 th AUGUST, 2024 ORDER :

1.

Heard.

2.

Since the applicant - acquiring body has deposited entire compensation amount, the application is allowed in terms of prayer clause "B"

[NITIN B. SURYAWANSHI] JUDGE drp/ca16241-16.doc