Union Of India Through The General Manager Central Railway Mumbai v. Ramkishan Dnyanoba Sanap And ORS
2025:BHC-AUG:12088 921.odt (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 13532 OF 2024 IN FAST/32042/2024 WITH CIVIL APPLICATION NO. 13535 OF 2024 IN FAST/32045/2024 Union Of India Through The General Manager Central Railway Mumbai and Ors
VERSUS
Ramkishan Dnyanoba Sanap And Ors ...
Advocate for Applicants : Mr. Ajay Gajanan Talhar Advocate for Respondents : Mr. R.N. Dhakane ...
CORAM : S.G. CHAPALGAONKAR, J.
DATED : APRIL 24, 2025 PER COURT :
1.
Heard learned advocates appearing for respective parties. 2.
Applicants seek to condone delay of 410 days caused in filing appeals against judgment and award passed by the Reference Court under provisions of Land Acquisition Act. 3.
Perused the applications and reasons as stated therein. It appears that delay is occasioned on account of administrative exigencies and procedural aspects that require to be followed by applicants. No malafides are discernible in making delay. The applicants have not derived any advantage by making such delay. Contents of civil applications are not controverted by respondents. In that view of matter, case is made out to condone the delay.
921.odt (2) 4.
Hence, civil applications are allowed. Delay of 410 days caused in filing appeals is condoned. Appeals be registered, subject to removal of office objections.
(S.G. CHAPALGAONKAR, J.) Mujaheed//