IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.17235 OF 2022 IN FIRST APPEAL NO.3005 OF 2022 The Executive Engineer, Hatnoor Project, Chopda ... APPLICANT

VERSUS

The State of Maharashtra & ors.

... RESPONDENTS .......

Mr. S.V. Munde, Advocate for applicant Mr. S.P. Sonpawale, A.G.P. for State Mr. V.B. Patil, Advocate for respondent No.3 .......

CORAM :

R. G. AVACHAT, AND R. M. JOSHI, JJ.

DATE :

22nd DECEMBER, 2022.

PER COURT :

This civil application is filed for extension of time for depositing 75% of the amount as per order dated 29/8/2022. Learned counsel for the applicant makes a statement, on the basis of contentions made in the Civil Application that, the applicant is depositing 14% of the amount from the amount directed under the above order. Considering the said fact, the Civil Application is allowed. Time to deposit the remaining amount is extended by eight weeks.

( R.M. JOSHI, J. ) ( R. G. AVACHAT, J. ) fmp/-