Saraswati Chandarrao Chandrakant Shitole v. The State Of Maharashtra And Others
12013.2015 WP.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO. 12013 OF 2015 ...
SMT. SARASWATI WD/O. CHANDARRAO @ CHANDRAKANT SHITOLE
VERSUS
STATE OF MAHARASHTRA AND OTHERS ...
Advocate for Petitioners : Mr. P.B. Shirsath AGP for Respondents/State : Mr. U.H.Bhogale Advocate for Respondent No.3 : Mr. D.G.Nagode Advocate for Respondent No.2 : Mr. S.T.Shelke ...
CORAM : S.S. SHINDE & P.R. BORA, JJ.
Dated: February 10, 2016 ...
PER COURT :- 1] The learned counsel appearing for respondent No.2 submits that, compliance regarding submission of certain documents and formalities remained to be done on the part of the petitioner. The learned counsel appearing for the petitioner, on instructions, submits that, the entire compliance of formalities will be completed on the part of the petitioner within two weeks from today.
2] In case such compliance is made by the petitioner, respondent No.2 shall forward the family pension proposal of the petitioner to the respondent No.3 within 4 weeks of such compliance by the petitioner. Respondent No.3 shall consider the said proposal and take decision within 8 weeks from receiving the proposal from the respondent No.2.
12013.2015 WP.odt 3] The entire exercise is to be done by the parties within 4 months from today. Petition stands disposed of. 4] Parties to act upon authenticated copy of this order.
( P.R. BORA, J. ) ( S.S. SHINDE, J. ) ...
DDC