Pandhari Bhujanga Mane v. The State Of Maharshtra Through Collector Osmanabad And Othes
934-CA-16445-2016.odt (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 934 CIVIL APPLICATION NO.16445 OF 2016 IN CRAST/37308/2016 PANDHARI BHUJANGA MANE
VERSUS
THE STATE OF MAHARSHTRA THROUGH COLLECTOR OSMANABAD AND OTHES ...
Advocate for Applicant : Mr. Ingale Vivekanand V. AGP for Respondents : Mr. S.D. Ghayal ...
CORAM : P.R. BORA, J.
DATED : 29th March, 2019.
PER COURT:- .
The applicant has filed the present application seeking condonation of delay which has occasioned in filing the Civil Revision Application by him. The delay caused is of 6125 days. Two reasons are assigned by the applicant to explain the delay; first that the Advocate who was appearing for him in the lower court did not intimate him about the dismissal of the reference application and the second that he is a poor agriculturist having no adequate financial resources.
2.
The delay caused is of the period of about 17 years. The reasons as are assigned to explain the delay are insufficient to condone the huge delay of around 17 years. I
934-CA-16445-2016.odt (2) am, therefore, not inclined to condone the same. Hence the following order:
ORDER
The application is rejected. Consequently, the Civil Revision Application (Stamp) No.37308 of 2016 also stands dismissed.
(P.R. BORA, J.) Mujaheed//