IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 14025 OF 2024 IN FAST/33779/2024 UNITED INDIA INSURNACE CO LTD THR DIVISIONAL MANAGER

VERSUS

ALKA SANJAY SHINDE AND ORS ...

Mr. Nikhil N. Narlawar h/f Mr. Suraj R Bagal, Advocate for Applicant.

...

CORAM : S. G. CHAPALGAONKAR, J.

DATED : 17th APRIL, 2025.

P.C.:- 1.

Heard Mr. Bagal, learned Advocates appearing for applicant. 2.

By this application, applicant seeks to condone delay of 36 days caused in filing Appeal.

3.

Perused reasons as stated in application. The delay appears to have been caused on account of administrative exigency. The applicant has not derived any advantage by making such delay. Hence, sufficient cause is made out to condone delay. Hence, following order:

ORDER

a.

Civil Application is allowed.

b.

Delay of 36 days caused in filing appeal is hereby condoned. c.

Appeal be registered subject to removal of office objections. (S. G. CHAPALGAONKAR) JUDGE Devendra/April-2025