Bombay High CourtCA/973/2016admittedallowedgrantedrule absolute

Executive Engineer, Lower Dudhna Project Div., Sailu Now Jalna Irrigation Div., Under Gmidc And ORS v. Achhut Saganaji Giram And Others

2016-02-24Hon'Ble Shri Justice T.V. Nalawade1 pages

-:(1):- FARAD CONTINUATION SHEET NO.

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD.

Office Notes, Office Memoranda of Coram, appearance, Court's orders or directions and Registrar's orders.

Court's or Judge's orders.

CIVIL APPLICATION NO. 973 OF 2016 IN FAST/37884/2015 EXECUTIVE ENGINEER, LOWER DUDHNA PROJECT DIV., SAILU NOW JALNA IRRIGATION DIV., U

VERSUS

ACHHUT SAGANAJI GIRAM AND OTHERS ...

Advocate for Applicant : Mr. Surwase B. R.

Advocate for Respondent Nos.1 to 3: Mr. Kakade D. M. *** CORAM: T. V. NALAWADE, J.

DATED: 24th FEBRUARY, 2016.

PER COURT:

1.

Heard both the sides.

2.

In view of the contents of the application and the submissions made, that some time was consumed for collecting certified copy, some time was consumed for processing the matter and some time was consumed for getting sanctions at various levels, this Court holds that sufficient cause is shown.

3.

In the result, delay is condoned. Application is allowed and disposed of accordingly.

[T. V. NALAWADE, J.] Dt.24/02/2016.