IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD FIRST APPEAL NO. 1758 OF 2016 THE GMIDC AURANGABAD THR THE EXE ENGINEER, LOWER DUDHANA PROJECT DKV., SELU AND ORS
VERSUS
MUKTABAI GANPATRAO BORADE ...
Advocate for Appellants : Mr. P.R Tandale Advocate for Respondent : Ms. Asha D. Rakh ...
CORAM : P.R. BORA, J.
DATED : 20th March, 2019.
PER COURT:- .
Not on board. Taken on board.
2.
The present motion is moved for speaking to the minutes of the order dated 07.03.2019.
3.
In the order passed by this Court on 07.03.2019 in First Appeal No.1758 of 2016, the following clause be added as clause 3-a:
"3-a. The amount deposited, if any, by the acquiring body in this Court is permitted to be withdrawn by the original claimant with interest accrued thereon".
4.
Corrected writ be issued accordingly. The motion stands disposed of.
(P.R. BORA, J.) Mujaheed//