The Oriental Insurance Co.Ltd v. Ambika Sushilkumar Jadhav And ORS.
14103.23CA
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 25 CIVIL APPLICATION NO.14103 OF 2023 IN FAST/36130/2023 WITH CIVIL APPLICATION NO.14104 OF 2023 IN FAST/36130/2023 WITH FIRST APPEAL STAMP NO.36130 OF 2023 THE ORIENTAL INSURANCE CO. LTD.
VERSUS
AMBIKA SUSHILKUMAR JADHAV & OTHERS ...
Advocate for Applicant : Mr.Dhananjay P. Deshpande ...
CORAM :ARUN R. PEDNEKER, J.
DATE :28.11.2023 P.C. :
A] ORDER IN CIVIL APPLICATION FOR DELAY 1] The present Civil Application is filed to condone the delay of 55 days in filing First Appeal.
2] For the reasons stated in the Civil Application, the same is allowed. Delay is condoned. Appeal be registered. Civil Application is disposed of accordingly.
14103.23CA B] ORDER IN CIVIL APPLICATION FOR STAY 1] The learned counsel for the applicant submits that the applicant has deposited 50% amount before the Tribunal.
2] There shall be ad-interim stay to the impugned award subject to deposit of remaining 50% amount as directed by the Tribunal within a period eight weeks from today along with accrued interest thereon till date before the Tribunal.
C] ORDER IN FIRST APPEAL Heard. Issue notice to the respondents returnable on 6th February, 2024.
[ARUN R. PEDNEKER] JUDGE DDC